Tuesday, October 15, 2013

Cabinets and Appliances

The cabinets throughout the kitchen and bathrooms have been assembled and installed. Closet organization has also been started, and the kitchen has been outfitted with all new stainless steel appliances including a beautiful double wall oven.

Friday, September 20, 2013

Thursday, September 5, 2013

Friday, August 30, 2013

Drywall

All the board was loaded in to the house and the installation was completed this week. Taping will start in a couple days.

Friday, August 23, 2013

Inspections

Paper and insulation was completed after the inspections were done. Due to some plumbing errors, we replaced 94 fittings, 150' of pipe and installed 32 metal plates to protect the plumbing. We also replaced 50% of the garage floor to accommodate the 7'9" garage opening.

Friday, August 9, 2013

Delays

There have been a lot of delays with the paper, wire and soffit installation. Unfortunately due to some no-shows from the owners contractors.

Saturday, May 18, 2013

Backfill & Steel Beams

Good progress this week, BC Hydro installed the temporary power and Regional District of Central Okanagan completed the water connection.  Back filling and re-grading of the driveway started Thursday, the steel beams were started Friday and will be completed after the long weekend.