Friday, August 30, 2013
Drywall
All the board was loaded in to the house and the installation was completed this week. Taping will start in a couple days.
Friday, August 23, 2013
Inspections
Paper and insulation was completed after the inspections were done. Due to some plumbing errors, we replaced 94 fittings, 150' of pipe and installed 32 metal plates to protect the plumbing. We also replaced 50% of the garage floor to accommodate the 7'9" garage opening.
Friday, August 9, 2013
Delays
There have been a lot of delays with the paper, wire and soffit installation. Unfortunately due to some no-shows from the owners contractors.