Thursday, April 18, 2013

Excavation

The excavation started April 18, good progress, removed the trees from the north edge of the lot and removed about 30 percent of the basement excavation material to start building up the access road.  Early next week, BC Hydro will advise the cost of underground v.s. overhead service to the house.  Temporary power is required for the site as soon as possible so we are pushing BC Hydro for prompt service.