Slow progress this week, some issues but all were resolved. The gravel bank towards the neighbours fence sloughed into the excavation and shifted the footings. We removed all of the footings in the lower garage area and brought in a small excavator to clear the gravel then reset the footings. On Wednesday the concrete pumper truck showed up late and didn't have enough equipment to do the job, the delay compromised the quality of concrete so we sent back an entire truckload of concrete and the pump truck. The owner of the pumper truck has taken responsibility for his error and will settle payment with the concrete company.
We expect to pour the concrete walls on Friday next week.